Distribute tasks between resources & projects
In this serie of articles devoted to visual management in project management, today we will discuss how to use the fever chart to manage a project portfolio. Talking about visual management … Let's take the graph below and see what we can observe: In most of the cases, you will rightly see that two projects … Continued
In this serie of articles devoted to visual management in project management, today we will discuss how to use the fever chart to manage a project portfolio.
Talking about visual management … Let's take the graph below and see what we can observe:

In most of the cases, you will rightly see that two projects are in trouble. They are not late (see the previous article) but are over-consuming the protection defined.
What are the options available?
- Can we take resources from projects 4/5/6 to help projects 1 & 7?
- Should we start the project 9?
- What benefits would we have from taking resources of 9 to allocate them to 1 & 7?
- A last (more playful) option sometimes emerges. We could freeze projects 1 & 7 and take resources to 4/5/6, so they finish even faster and then put everyone back on 1 & 7. It's more playful, but it can work.
During the trainings, sometimes some participant tell me that it is not possible to mix resources.
Yes... However, we often observe that the projects are different but that the range for designing the project is ultimately quite similar.
So, if you take the previous chart, you will find that P1 / 2/7/8 have some proximity.
Thus, even if P4 / 5/6 can't help, maybe P2 / P8 can help.
In the following article, we'll see how this fever chart can help you make history for your project.
In the meantime, if you have any questions or if you want to discuss with our experts on this topic, fell free to contact us! contact@agilea-group.com
Go further
Related articles
Flow Project Management
S02-E05 Managing the Load / Capacity of the Softs (the continuation of the precisely wrong)
At this point, everything is going well: But, there are several projects that use the same resources. So, how do you manage this? Most people will tell you that having a project management tool that collects load and capacity will help you drive your choices. This is simply not true. Most load / capacity tools … Continued
Flow Project Management
S02-E04 How do I focus on the right tasks for my project?
Once you have completed your project plan, sized the tasks and avoided creating a labyrinthine system with too much detail, you need to move on to the step that will identify the most time critical task sequence. At this point, we recommend that you use the critical chain approach. Unlike the critical path approach, which … Continued
Flow Project Management
S02-E03 The world of precisely wrong with the project plan
You made your project plan (episode 1). Then you verified that it was at the right level of detail (episode 2)... knowing that there is an uncertainty that you will discover. How will/should you incorporate these elements into the project plan update? Whoa, slow down! We are going to integrate EVERYTHING into the schedule, aren't … Continued
Does this article resonate?
Let's talk about your situation.
Our consultants help you translate these reflections to your Supply Chain and your teams — diagnosis, scoping or operational delivery.